The list of FAQs, which contains questions for the current Framework Programme (Horizon Europe), is updated with questions taken from the Marie Sklodowska-Curie Actions Q&A Blog. Make sure that you visit the blog for the latest FAQs on MSCA.

For MSCA FAQs pertaining to the previous Framework Programme (Horizon 2020) visit the old blog which the project will also update on a regular basis.

Filter by Action
Filter by Phase
to

COFUND

Timesheets and declarations are not requested in MSCA projects (contrary to other Horizon Europe actions based on actual costs). To prove that the researcher worked on their MSCA project, it is sufficient to present a contract with the host institution together with additional documents proving the fellow’s dedication to the project, if needed.

Moreover, declarations are not allowed by the auditors. REA has confirmed that the declaration on exclusive work is not applicable for audits carried out in MSCA ITN, IF and COFUND actions to determine time spent working on the action. It is expected this will continue in Horizon Europe.

As outlined in the H2020 Indicative Audit Programme, such evidence may include lab books, attendance lists, conference abstracts, library records, travel expenses, timesheets, reports to supervisor, meeting minutes, e-mail exchanges, etc. and other open sources (e.g. the internet) to see if the researcher worked on activities other than their  project. The auditors will also look at the researcher’s employment contract or corresponding agreement to see if it complies with Article 32 of the H2020 Annotated Model Grant Agreement, including but not limited to the obligation that the researcher works exclusively for the action.

Fellows need documentation in the form of a contract that shows the 50% commitment or something similar since MSCA does not typically operate with timesheets.

A COFUND project can be designed in many different ways and it is up to the beneficiary to decide how the researchers are funded. If the beneficiary wants to include a family allowance after the recruitment, it is OK, but it is not a formal requirement from the EC/ REA. It can of course be evaluated positively by the evaluators as clear support to offer the best conditions to the fellows. In addition, this would be unlikely, as in H2020 the MSCA rules did not foresee changes in the eligibility for family allowance during the fellowship duration.

“Partner Organisations” means both type of partners: associated or implementing.

Implementing partners have a bigger role, however, this was harmonised among the MSCA actions and associated partners are supposed to appear in part A for all actions. COFUND is the only action which has implementing partners and therefore it is slightly different.

Doctoral Networks

For calls with deadlines in 2022 and beyond, once a project proposal is selected for funding following evaluations, consortium partners concerned by the eligibility criterion will have until Grant Agreement signature to confirm they have a GEP in place.

For calls with deadlines in 2022 and beyond, once a project proposal is selected for funding following evaluations, consortium partners concerned by the eligibility criterion will have until Grant Agreement signature to confirm they have a GEP in place.

This is mainly for statistics purposes.

The maximum amount for DN is up to 1 page. For PF it is up to ½ page. This is a maximum that is indicated and not expected.

For DN it applies to the proposal as a whole.

For PF, as of 2022, proposals involving the same beneficiary and individual researcher submitted to the previous call of MSCA Postdoctoral Fellowships under Horizon Europe and having received a score of less than 70% must not be resubmitted the following year.

MSCA & Citizens (Night)

Timesheets and declarations are not requested in MSCA projects (contrary to other Horizon Europe actions based on actual costs). To prove that the researcher worked on their MSCA project, it is sufficient to present a contract with the host institution together with additional documents proving the fellow’s dedication to the project, if needed.

Moreover, declarations are not allowed by the auditors. REA has confirmed that the declaration on exclusive work is not applicable for audits carried out in MSCA ITN, IF and COFUND actions to determine time spent working on the action. It is expected this will continue in Horizon Europe.

As outlined in the H2020 Indicative Audit Programme, such evidence may include lab books, attendance lists, conference abstracts, library records, travel expenses, timesheets, reports to supervisor, meeting minutes, e-mail exchanges, etc. and other open sources (e.g. the internet) to see if the researcher worked on activities other than their  project. The auditors will also look at the researcher’s employment contract or corresponding agreement to see if it complies with Article 32 of the H2020 Annotated Model Grant Agreement, including but not limited to the obligation that the researcher works exclusively for the action.

Fellows need documentation in the form of a contract that shows the 50% commitment or something similar since MSCA does not typically operate with timesheets.

When talking about impact, this is prospective, it is in the future, assuming that the project is successful and that it achieves everything that it set up to achieve. The applicants could base themselves on some other studies to strengthen or build their case about the impact they could have, before the impact is actually achieved.

There are different scientific panels and proposals are ranked within their scientific panel. Proposals in some panels are more STEM-oriented and would have a different kind of impact than proposals in the SOC panel for instance, but these proposals would not compete against the STEM-oriented proposals. It should also be considered that the impact is now broadened to encompass not only a purely scientific impact but also impact on the society at large. This can be an area where the SSH proposals could actually have a competitive advantage.

The first thing to note is, that even though they cannot directly claim costs, it does not mean that they cannot indirectly receive some funding for the role they have in the DN. Typically for each unit cost, there is one part that goes to the researcher and then there is the institutional part, and this part should not be seen as funding for just this particular fellow, and this beneficiary. It is rather a common pot for the whole consortium to run the project. In the consortium agreement the consortium defines how this is split. This funding can be distributed to the different partners according to their needs in the project: some partners provide more trainings, for instance, the coordinator typically has more management costs, so this funding can be redistributed, and some of this money can go to associated partners to cover the costs of them hosting researchers for secondments, or for them to provide trainings. So these are internal arrangements within the consortium (in the broader sense with the associated partners) so they can get indirectly money for their action. Of course, there are also non-financial incentives; the interest for them to participate could be transfer of knowledge or being part of a dynamic network and being associated to the research project.

For PF, direct financial benefits may not be there but there are plenty indirect benefits – scientific contributions, networking, getting experience in this type of projects, hosting events.

Postdoctoral Fellowships

They would need to discuss this with the project officer, and they can approve or refuse the request. Part time working has to be calculated on a weekly basis as the payments are based per person month. For 6 months on, 6 months off, they would need to suspend the project for the 6 months they are not working on the MSCA fellowship.

It is the physical presence (residence or main activity) in a given country that is taken into account when considering the mobility rule. If they have not resided or carried out their main activity in country A for more than 12 months in the last 36 months, they are eligible.

As the rule states that ‘The researcher must be in possession of a doctoral degree or have successfully defended their doctoral thesis before call deadline’, the time scheduled for the defense would indeed count in this context. The defense should end successfully before 5 pm CET on day of the call deadline.

Proposals from Global Fellowships to European Fellowships or vice versa from European Fellowships to Global Fellowships are not considered resubmissions.

The official residency of the applicant is the one to consider for eligibility purposes. This needs to be clear in the application forms.

Staff Exchanges

Associated Partners are entities, which participate in the action, but without the right to charge costs or claim contributions. They contribute to the implementation of the action, but do not sign the grant agreement. They must include a letter of commitment. Therefore, in SE they could send and host secondments, but they cannot claim costs.

Yes, the type of link and the activities of the Associated partners linked to a beneficiary should be indicated in Part B, and they will be assessed as part of the evaluation.

It depends because some proposals can be very similar, for instance in the case of resubmission; and others are not quite similar, but they are still considered similar, for instance in the case of continuation. Even if the applicant mentions that a similar proposal has been submitted, this will be checked very carefully by REA. If after checking REA sees it is not the case, they will not consider it to be similar.

On the Funding and Tender Opportunities Portal there is a possibility to find interested associated countries or member states, it depends on the exchange. In case of an exchange between a member state and an associated country (a beneficiary and a 3rd country part), one can find whatever organisation. There however cannot be any exchange between two associated partners.

The list of organisations is in form A. REA avoids including the list of organisations at the beginning of part B. All participating organisations in SE projects need to be included in part A, which is the predominant list of beneficiaries and associated partners.